(g)
Contractual Rights and Access to Inform ation
During the visits it emerged that the terms of resettlement, particularly the amount of
compensation provided to affected households, was different in each case. It
appeared to be a frequent tactic of government to make an offer of a fairly low
compensation amount, wait and see if the community would accept, then proceed to
offer higher compensation amounts until an agreement is reached. According to
standard 3.11, compensation may indeed be different in each case of resettlement,
depending on the nature and degree of losses suffered during the eviction and
resettlement process. However, the distribution of financial damages must be
according to clearly stipulated criteria and should be to compensate for losses actually
suffered. Compensation should not be employed by government as a negotiating tool
to induce communities to accept resettlement on its terms. This manner of financial
enticement can prejudice communities who lack the bargaining position to effectively
engage with government, particularly those who are not organised.
Resettled communities consistently reported insufficient or no access to documentary
evidence of their proprietary interest in the resettlement site. The process in NHAmanaged resettlement sites was to only provide the contracting party with a stub which
indicated their house and lot number in the site. This was the only evidence they
possessed of their amortisation agreement. Many individuals were denied access to a
copy of the agreement, or were advised that they would only be permitted to view one
upon payment of a considerable fee. To comply with standard 2.2 in resettlement
sites, government must take immediate measures to confer legal security of tenure on
those subject to resettlement. Households must have access to the documentary
evidence on which this tenure is based to be able to identify the nature and scope of
their legal interest in the property and enforce that interest against all other parties.
Many community members also reported signing amortisation agreements under
duress, or with no understanding of the financial implications of the amortisation
process. Many individuals required to sign contracts were illiterate or unable to speak
English, but nonetheless were required to sign an English language version of the
contract and were provided with no opportunity to consider its terms or seek external
advice. According to standard 3.12, comprehensive information about all aspects of
the resettlement must be provided to those affected prior to the eviction and
resettlement process. This will include ample opportunities to seek legal and
professional advice on the implications of any contractual obligations that will arise.
The Government must ensure that copies of the amortisation agreement are supplied
to affected individuals well in advance of their resettlement, so that they are able to
fully consider all financial and legal aspects of the amortisation. The Government must
also institute measures to ensure that individuals are fully aware of their obligations
under the agreement prior to signing, by providing materials in a language that they
understand or providing services for independent translations or consultations.
There were many difficulties experienced by resettled communities visited in meeting
the conditions of the amortisation agreements. Particularly difficult was the apparent
restriction in the amortisation agreement on transferring the interest in the site in any
way, effectively forcing residents to remain in the resettlement site despite the absence
of services and economic opportunities. Many residents of resettlement sites reported
starvation or other severe financial hardship as a result of resettlement. Standard 3.12
104 Human Rights in the Rubble