176 i COMPLAINTS BEFORE THE COMMISSION
The High Court subsequently appointed a Special Investigation Team (SIT) to
make an inquiry into the incident. The SIT constituted by the Court has submitted its
report. The report states that the concerned Army unit has refused to hand over the
accused Major Avtar Singh to the SIT. The matter continues to be subjudice before the
High Court, a notice having been served against the Army for the production of the
accused before the High Court.
The Commission has raised this matter repeatedly in its annual report and with
the senior most echelons of the army. It intends to pursue this matter, but has to await
the outcome in the High Court.
OTHER IMPORTANT CASES
26) Death due to Electrocution — Strict Liability of the State:
Jharkhand (Case No.1509/4/2000-2001)
The Commission took cognisance of a complaint from Maku Murmur, resident
of Dumka, Jharkhand alleging that her husband, Babu Ram, had died on 9 July 2000 as
a result of being electrocuted by a live transmission wire. She stated that the death was
the result of negligence of the Bihar State Electricity Board.
Upon a notice sent to the Chairman, Bihar State Electricity Board as well as to
the District Magistrate, Diunka, it was confirmed that the victim had died after being
electrocuted. It was, however, contended that a severe storm had occurred on the date
of the incident and that deceased might have come into contact with the electricity
wires, which would have fallen to the grotmd because of the storm and rain. It was
stated that the death had not resulted from the fault of any person of the electricity
department or any other authority.
The Commission, while over-ruling the contentions of the State, held that the
Bihar State Electricity Board could not be absolved of its responsibility of properly
maintaining the whole system; that rain and storms were not an unusual
phenomenon and care was needed to avoid such situations. Accordingly, the
Commission in its proceedings dated 29 August 2001 issued a notice to the State of
Bihar to show cause why immediate interim relief u/s 18(3) of the Protection of
Human Rights Act, 1993 be not awarded to the petitioner.
NATIONAL HUMAN RIGHTS COMMISSION
Select target paragraph3
Connect to a paragraph
Connect to an entity
Disable highlights
Add to table of contents