Agropolitan and MESEJ projects for hardcore poor
6.57 Many of the indigenous land development schemes are related to poverty reduction through
the introduction of plantations and infrastructure. The Ministry of Rural Development (MRD)
together with District Offices in the State has been tasked with the identification of hardcore
poor communities, while the Sabah Economic Development and Investment Authority (SEDIA)255
channels funds it receives from the Federal Government under the Sabah Development
Corridor (SDC). Poverty eradication programmes focusing on indigenous land development
projects include the Agropolitan and Mini Estet Sejaterah (MESEJ) projects.
6.58 Communities affected by these projects describe them as top-down programmes with
no consultations or consent-making mechanisms for the project. The Inquiry noted and
commented on the lack of verifiable and adequate information to the affected communities
on an ongoing basis, as well as a transparent process to select the hardcore poor. Taking
land from other members of the community and giving it to landless hardcore poor could
lead to intra-community conflicts. The Inquiry fails to see how such projects could ensure
social and sustainable development, which is among the main objectives of the project and
of SEDIA.256
6.59 In case no KM24, Mr Marajim@Ejim b Mangkong (W34) representing two villages in Indarason
Darat and Minikodong in Kudat said 733.4 acres of land for their livelihood had been taken
for the MESEJ project by MRD in early 2006 without any LE or proper consultations. When
the contractor started work, their crops and graveyards were destroyed and each time the
road to the project was upgraded, their water pipes were disconnected and destroyed. No
compensation was paid for these acts of destruction.
6.60 Ahmad Shah bin Kalon, West Coast District Surveyor in responding to the W34 said “...MRD
applied for 500 acres of land in Kg Minikodong and followed the normal process whereby the
land application was brought to the LUC and was supported. Subsequently, a survey order
was made to the district surveyor dated 3 August 2009, a file opened in 2005 SP0558220 and
the survey completed. On 28 November 2006, the survey plan 05125665 was approved with
an area of 526.3 acres. For the next process, we submitted to the Natural Resource Office
and MESEJ Minikodong was gazetted under gazette number 356/2008 ....It was gazetted
under Section 28 of Sabah Land Ordinance for “public purpose” that is Mini Estet Sejatera
(MESEJ) project”
6.61 In a similar case (TW26), Mr Sappari Saidal (W67) from Kg Bakong-Bakong, Semporna,
expressed dissatisfaction in the slow process of obtaining approval for his community’s land
application, which he submitted in 1994, but which resulted in their NCR land being gazetted
under section 28 of the SLO in favour of MRD for conversion into a MESEJ project. According
to the Tawau district surveyor, Mr Abdul Manap b Aneh (W75), the LSD was aware that Kg
Bakong-Bakong was occupied but the LSD Director himself gave the go-ahead to MRD to
enter the area.
6.62 In case no KM78, in responding to Ms Salmah bt Marail (W37) from Kg Timbang Dayang,
Banggi in Kudat, the Director General of FELCRA, Tuan Haji Samian Hj Mohd Ali (W38) said
that discussions regarding the Agropolitan project in Banggi Island were held with village
255 SEDIA was established in 2009 for the purpose of promoting the Sabah Economic Development Corridor (SDC) and governed by